Operational Highlights

In 2008, the ERCB was responsible for regulating

  • 175 172 operated wells
  • 797 gas plants
  • 4613 compressor stations
  • 14 764 gas batteries
  • 412 555 kilometres of pipelines

Applications

  • 43 775 applications were submitted to the ERCB
  • 1.1 days was the average turnaround time for routine facility applications

Inspections

  • 18 667 inspections were conducted

Hearings

  • 20 hearings were held

Drilling

  • 15 417 wells were drilled

Pipelines

  • 9011 kilometres of pipelines were added